patching...
Welcome back, Patch Blogger!

White Lake Township Mulls Sewer Debt Options

The township met Tuesday to get a history of the sewer projects in White Lake, a background on the bonds and sewer fund, and to discuss future solutions to current problems with the sewer fund.

 

The White Lake Township Board of Trustees continues to wrestle with the potential funding shortfall in the township's sewer fund. Township Supervisor Greg Baroni says the township has enough money for the 2012 debt repayment, but that the board needs to make some decisions so the fund will continue to bring in enough money to pay back the debt owed from the township’s sewer project that started in the 1990s.

Clerk Terry Lilley said the presentation on the history of the project, and the subsequent sewer fund discussion, was necessary because it had been brought up during the campaign in August, and several people running for office at the time had inaccurate information.

At a board meeting Tuesday, Supervisor Baroni explained, “There were times at township meetings when candidates said there was no money in the fund, and that the township wouldn’t be able to repay its debt. That simply isn’t true. But, we do need to look at the fund and make some changes so that we don’t run into problems in the future. It’s something that’s been kicked down the road from one administration to the next, now we need to take some action.”

Lilley said the ongoing issue dates back to the 1990s, and that some of the decisions made in the 1990s by previous administrations have tied the hands of the current administration and put the township in the situation it’s in now.

“That is why it is so important for us to go back, look at the decisions that were made, and see where things went wrong,” Lilley said. “Those mistakes can help us now so we don’t make the same mistakes in the future.”

Part of the problem, Lilley said, is that the township was bringing in money in the late 1990s and early 2000s from the Phase 1 project, but the board at that time decided to use those funds to subsidize the sewer project along Pontiac Lake, instead of keeping it to pay for the first phase of the township’s sewer line.

“As a result, the debt grew because money was taken from one project to pay for the other instead of letting that project pay for itself through the collection of fees," Lilley said. "There were project overages as time went on, and those funds that were taken from phase one were never paid back, putting that project further in debt.”

Another issue, according to Lilley, is the projection that initial direct and indirect sewer hookup funds would have paid the debt through 2014, and earned interest at a steady 4 percent. Instead, the fund is earning only .4 percent interest.

Lilley presented the township board with four possible solutions to keep the sewer fund in the black. None of the options were discussed at length Tuesday, but they will be in the coming months, with the new board taking over in November, Baroni said.

Those options include:

  • Unscrambling the current accounting issues. This would mean that Pontiac Lake property owners would have to be assessed for any and all deficiencies related to its project funding, Lilley said, and also means holding reassessment hearings for all 432 parcels within the sewer district at $1,900 per parcel.
  • Allowing the Pontiac Lake sewer fund to collect indirect fees to meet its requirements for bond repayment. If there are any remaining funds after debt is paid, those would be returned to Phase 1. This would mean that Phase 1 will never benefit from whatever indirect fees it was shorted, creating shortfall in customers and cash flow prior to bonds being fully paid in 2018.
  • Loaning improvement revolving funds to meet principal and interest demands on Phase 1 bonds each year through 2018.
  • Increasing the debt service charge and connection fees to make up some of the potential deficit.

The Numbers

Phase 1 Sewer Project (1995)       
Proposed Project Funding Proposed Construction Costs
State Revolving Fund $9,350,000 Construction Costs $7,100,000
Oakland County Drain Commissioner $725,000 Engineering Costs $725,000
Total $10,075,000 803 Prepaid Commerce Taps $2,250,000
Total $10,075,000
Actual Project Funding Actual Construction Cost
State Revolving Fund $9,350,000 Construction Costs $7,657,714
Oakland County Drain Commissioner $725,000 Engineering Costs $1,011,855
Interest Earned on Bond Money* $59,312 775.86 Prepaid Commerce Taps $2,250,000
Total $10,134,312 Total $10,919,569
Total Cost Overrun $785,257
Cost Overrun Paid Via:
Transfer from Improvement Revolving $400,000
Taken from Sewer Debt Repayment Fund $385,257
Total $785,257

*Interest earned from 1995 Through 1998 on bond money received and prior to being disbursed.

Projected REUs* Amount
Direct 1,362 $5,175,600
Indirect 445 $845,500
Total $5,924,580
Actual REUs Amount
Direct 859 $3,263,440
Indirect 1,099 $2,087,340
Total $5,361,211

*REU stands for Resident Equivalency Units, this is the measurement used for sewer systems.

Phase 1 Revenues and Debt Service:

Inception Through Year End 2012

Proposed Revenues Actual Revenues
Special Assessments (connection fees) $5,663,011 Special Assessments (connection fees) $3,335,742
Pontiac Lake White Lake Township Connection Fees (431 REUs) $887,142 Pontiac Lake White Lake Township Connection Fees (62.08 REUs) $117,936
O.C. Debt Payments/Interest $1,989,592 O.C. Debt Payments/Interest $2,281,372
Commerce Connections $4,650,260
Commerce Connections
$4,896,367
White Lake Connections $1,643,500
White Lake Connections
$2,970,927
Total Proposed Revenues $14,833,505
Total Actual Revenues
$13,602,344
Proposed Expenses Actual Expenses
Commerce Connection Fees $3,710,260 Commerce Connection Fees $3,957,449
Debt Service Payments $9,080,758 Debt Service Payments $9,2000,095
Transfer to Construction Fund (1999) $385,257
Total Proposed Expenses $12,791,018 Total Actual Expenses $13,542,801
Proposed 2012 Fund Balance $2,042,487 Forecasted 2012 Fund Balance $59,543
Related Topics: White Lake Sewer, White Lake Township Board, and White Lake government

S.

8:28 am on Friday, September 28, 2012

When I was forced to hook up in 2000 on phase one, White Lake Township said their assessment program was closed and I must pay cash, hence, $8,000.00 to the township and $2,000.00 to a contractor to hook up my house. When I first signed up in 2000, my quarterly fee was $88.00. Now, in 2012, my quarterly fee is $155.50. Really, $622.00 a year just for sewer. So, the funds have been misused/abused and the next step will be to up our fees even more. When I had a septic, I paid about $125.00 every couple years. This is too much and the costs need to come down. Can I just put in another septic tank???

Reply

Bill Johnson

6:56 pm on Friday, September 28, 2012

Dear Laura Vogel: This one meeting you should have been at, that is if you wanted to find out what was really going on, you missed alot of interesting info.

Reply
Comment_arrow

Laura Vogel

10:09 am on Friday, November 9, 2012

sorry, Rog L., I was obviously unable to attend. Hopefully, our full-time paid elected officials will provide full information on e.g. the website so that citizens whom are unable to attend can otherwise still be informed. The historical information aluded to above and over the past several months is apparently currently hard to come by, even within the township's own paper records. So I'm hopeful that the digging around that is being done for this will have the added benefit of making the hopefully eventually found data readily available going forward.

Comment_arrow

Laura Vogel

10:09 am on Friday, November 9, 2012

to that point:
~~~
“That is why it is so important for us to go back, look at the decisions that were made, and see where things went wrong,” Lilley said. “Those mistakes can help us now so we don’t make the same mistakes in the future.”

Part of the problem, Lilley said, is that the township was bringing in money in the late 1990s and early 2000s from the Phase 1 project, but the board at that time decided to use those funds to subsidize the sewer project along Pontiac Lake, instead of keeping it to pay for the first phase of the township’s sewer line.

“As a result, the debt grew because money was taken from one project to pay for the other instead of letting that project pay for itself through the collection of fees," Lilley said. "There were project overages as time went on, and those funds that were taken from phase one were never paid back, putting that project further in debt.”

~~~
I am presuming there are records to show who recommended this bit of fiscal management?

Comment_arrow

Gerry Szumiak

2:12 pm on Friday, November 9, 2012

This is one meeting that everyone in the township should have attended Rog and that is the reason verbatim transcripts or video telecasts of all meetings should be available to the citizens of White Lake.
Carol Burkhard has told me that she is permitted to Skype her presence into meetings and that means the meeting is Skyped to Carol in real time to her home or hospital bed. Why not make the Skype transmission available to everyone?
It can be easily recorded and a copy posted to the township's website.

Comment_arrow

Laura Vogel

2:27 pm on Friday, November 9, 2012

Good point.
The meetings have microphones and presumably are being recorded. I'm not sure what they're being recorded on, however, nor who has those recordings nor what they're used for. Also, there is a transcriptionist taking shorthand of everything said. Again, not sure who gets those transcripts nor what are done with them. As taxpayers, we are paying for all of this, but are apparently not getting much citizen benefit from it.

Comment_arrow

Laura Vogel

11:27 am on Wednesday, November 14, 2012

FYI, the "second meeting" was last night, and no microphones were used nor was there any transcriptionist present. Since I wasn't at the first meeting, I cannot speak to whether the first meeting had microphones or the transcriptionist as is usually the case at the other/typical Board meetings.
http://whitelake.patch.com/articles/white-lake-township-to-hold-second-sewer-meeting

Bill Johnson

6:56 pm on Friday, September 28, 2012

Where were all the Pontiac Lake people?

Reply

Lakeside

11:45 am on Friday, October 5, 2012

I think Mr. Baroni better learn how to read a balance sheet. Forecasted 2012 fund balance $59,543 and a debt payment of close to $600,000 due in February. It appears the only way the fund can make its 2013 payment is to borrow the money. The figures do not lie. Also, I obtained a copy of the budget and the sewer fund is the responsibility of the Supervisor yet Clerk Lilley appears to be steering the ship.

Reply

Bill Johnson

12:06 pm on Friday, October 5, 2012

Dear Mr. Lakeside: You just know learned that the township has to borrow money to pay the debt or they can go back and reassess the Pontiac Lake Homeowners and make them backback the $1900 that the Superviser Bonnie Elliot gave them when she was in office.

Reply

Lakeside

1:21 pm on Friday, October 5, 2012

It appears the cadidates Baroni made reference to were correct about the fund being broke. I can't help but wonder what he would have done if this isssue was not pushed by some of the candidates. Also, as far as I can tell this problem is going to happen every year for the next six years until the bond is paid off. I am not sure how many homes are in the Pontiac Lake area, but they are going to need close to $2,000,000 in additional money over the life of the bond.

Reply
Comment_arrow

Bill Johnson

4:37 pm on Friday, October 5, 2012

Please read the above article and you find how many homes are in the Pontiac Lake area.

Lakeside

1:32 pm on Monday, October 8, 2012

The Pontiac Lake 432 homes times $1,900=$820,800. That amount is not even half the money they need.

Reply

Bill Johnson

7:39 pm on Monday, October 8, 2012

How many connection fees would they have to pay off the bond? (both direct and indirect)

Reply

Lakeside

9:42 am on Tuesday, October 9, 2012

I am not sure, I heard one of the board members mention mandatory connects. However, there is a labor cost associated with the White Lake end so it would be interesting to know how much of a connect fee is profit. This is a real mess, that could drain a lot of money. I also heard one of the board members mention how high the Commerce fee is for residential (close to $5,000). It's too bad some board members covered up this information before the primary, it might have changed some of the votes.

Reply

Bill Johnson

10:11 am on Wednesday, October 10, 2012

I wonder how the water dept. have a 4 million in their water fund, what kind of profit they are making, how can that be possible?

Reply

Lakeside

10:21 am on Monday, October 15, 2012

That is a good question for your elected officials. It amazes me Lilley had all this history yet he did not say anything for the last eight years while the problem was snowballing. One trustee brought this up and nobody else said a word.

Reply

Leave a comment